When and where revalidation is required?


Revalidation means that the original validation program should be repeated at a predetermined frequency. This work is carried out 3 years interval & any change of critical steps or process.

i.  Changes in raw materials (Physical parameters such as viscosity, density, moisture & Particle size distribution) may affect the products & process
ii.      Changes in the sources of active raw materials manufacturer
iii.     Changes in the packaging materials (Primary packaging/Closure system)
iv.     Changes in the processes (e.g. mixing time, dry time, drying temp.& batch size)
v.      Changes in the equipment (e.g. addition of automatic electric system)
vi.    Changes in the plant or facility
vii.     Variation revealed by trend analysis.